Question 1
Question
Based on which object does production with repetitive manufacturing take place?
Please choose the correct answer.
Answer
-
Production order
-
Purchase requisition
-
Process order
-
Planned order
Question 2
Question
The SAP Kanban procedure could be used to trigger which of the following kinds of replenishment?
There are 2 correct answers to this question.
Answer
-
Subcontracting
-
Stock transfer
-
Vendor consignment
-
In-house production
Question 3
Question
What are the key aspects of SAP S/4HANA?
There are 2 correct answers to this question.
Answer
-
SAP S/4HANA is built on SAP HANA
-
SAP S/4HANA can be deployed on-premise, in the cloud, or a combination of both.
-
SAP S/4HANA has minor changes on data model.
-
SAP S/4HANA increases the data footprint.
Question 4
Question
You run MRP for a material that was planned using Demand-Driven Replenishment. Towards which buffer level does the MRP run create a replenishment proposal?
Please choose the correct answer.
Answer
-
Top of Red
-
Top of Green
-
Top of Red Base
-
Top of Yellow
Question 5
Question
How many files can you connect to a document info record?
Please choose the correct answer.
Question 6
Question
Which indicator in the material master determines if a material is relevant for advanced planning?
Please choose the correct answer.
Answer
-
Advanced Planning indicator
-
MRP type of material
-
Individual/collective requirement
-
Availability check of the finished product
Question 7
Question
Which chart types does the tabular planning table provide in SAP S/4HANA?
There are 2 correct answers to this question.
Answer
-
Orders (dispatched) chart
-
Work center capacities chart
-
Order (pool) chart
-
Capacity requirements chart
Question 8
Question
What are major reasons for the SAP S/4HANA Enterprise Management system?
There are 3 correct answers to this question.
Answer
-
It offers analytics with real-time data.
-
It includes CRM, SRM, and APO.
-
It provides a scalable infrastructure.
-
It is based on stable core ERP processes.
Question 9
Question
Which time elements can be reduced by a reduction strategy?
There are 3 correct answers to this question.
Question 10
Question
In which of the following master data objects can you define the production order default storage location for a material component?
There are 2 correct answers to this question.
Answer
-
Work center, in the production supply area
-
Material master of the finished product
-
Routing, in the component allocation
-
BOM, in the item for the material
Question 11
Question
Where do you maintain the work center that represents the production line for repetitive manufacturing?
There are 2 correct answers to this question.
Question 12
Question
You use planning strategy Finite Scheduling - with Reverse and want to allow scheduling in the past. How can you achieve this?
Please choose the correct answer.
Answer
-
Specify a negative offset time in the strategy profile.
-
Specify a positive planning horizon in the strategy profile.
-
Specify a negative planning horizon in the strategy profile.
-
Specify a positive offset time in the strategy profile.
Question 13
Question
With reference to GR, which statements are correct?
There are 3 correct answers to this question.
Answer
-
With GR, the system updates the Delivered Quantity field in the production order.
-
The automatic GR can be posted only with final confirmation. With partial confirmation, automatic GR won't be posted.
-
GR can be manually or automatically posted for an order.
-
Confirmation is the prerequisite step before GR. You can post GR for the quantity you finally confirmed.
-
The Delivery Completed indicator in the Goods Receipt tab page of the production order is set after the GR for the full quantity is posted.
Question 14
Question
The end user is working on a production order but can't post GI for the order, encountering error message Current order status does not allow goods withdrawals. The user then tried to confirm the order and again encountered an error. The Order is not released.
What is the next course of action the user should take?
Please choose the correct answer.
Answer
-
Try to post GR, and the error may be resolved.
-
First, print the shop floor papers.
-
Delete the order because there are so many errors in it.
-
First, release the order.
Question 15
Question
Which of the following belong to supply chain master data objects?
There are 2 correct answers to this question.
Answer
-
Vendor
-
Distribution center
-
Product cost collector
-
Account
Question 16
Question
Which statements are correct for MRP Live?
There are 2 correct answers to this question.
Answer
-
SAP S/4HANA simplifications eliminated planning file entries, so they aren't relevant for MRP Live.
-
Project planning and make-to-order planning for sales orders aren't optimized for MRP Live.
-
MRP Live creates MRP lists
-
All materials for all the plants can be planned.
Question 17
Question
You want to schedule an operation finitely, without moving other operations. Which scheduling strategy do you select?
Please choose the correct answer.
Question 18
Question
Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?
Please choose the correct answer.
Answer
-
When alternate resources are used within one operation
-
When multiple production versions are maintained for one product
-
When multiple planned orders exist on one resource
-
When multiple operations are maintained for one product
Question 19
Question
What are key benefits of SAP S/4HANA MRP Live?
There are 2 correct answers to this question.
Answer
-
Significantly higher data footprint leveraging SAP HANA
-
Runs on any device
-
Simultaneous capacity planning by default
-
Real-time analysis of disruptions in the material flow
Question 20
Question
At which level does detailed scheduling (DS) heuristics plan?
Please choose the correct answer.
Answer
-
Product
-
Resource
-
Vendor
-
Order
Question 21
Question
How can you create a production order?
There are 3 correct answers to this question.
Question 22
Question
What are the three transition scenarios for an S/4HANA implementation?
There are 3 correct answers to this question.
Answer
-
Landscape transformation
-
System upgrade
-
New implementation
-
System activation
-
System conversion
Question 23
Question
Which materials have a negative quantity in a bill of materials or in a recipe?
There are 3 correct answers to this question.
Question 24
Question
The method in which a production order is credited or debited depends on the variant of cost object controlling (COC). What basis can be used to carry this out?
There are 2 correct answers to this question
Answer
-
Order-related
-
Cost-related
-
Milestone-related
-
Product-related
Question 25
Question
For planning strategy 40 (planning with final assembly), if you don't maintain the consumption parameters, what happens to the PIRs?
There are 2 correct answers to this question.
Answer
-
If no consumption parameters are maintained, the system will check the consumption parameters in the MRP group assigned to the material.
-
The customer requirements will consume the PIRs first in the past and then switch to future.
-
The customer requirements won't consume PIRs.
-
If no consumption parameters are maintained, then the default setting is backwards consumption for 999 days.
Question 26
Question
What does a line hierarchy in repetitive manufacturing represent?
Please choose the correct answer.
Answer
-
A production line with a parallel sequence in the routing
-
A production line with an alternative sequence in the routing
-
A production line with prioritized alternative work centers
-
A production line with more than one work center
Question 27
Question
The production order default storage location for components can be defined in which of the following master data objects?
There are 2 correct answers to this question.
Answer
-
Location field maintained in the work center
-
Routing, in the component allocation
-
Material master of components
-
BOM item details
Question 28
Question
Capacity planning is available in which of the following areas?
There are 3 correct answers to this question.
Question 29
Question
You want to use capacity availability checks for production orders. Which settings have to be made for this?
There are 2 correct answers to this question.
Answer
-
An overall profile must be assigned in the checking control.
-
The PRT Availability Check must be set in the checking control.
-
The Relevant for Finite Scheduling indicator must be set.
-
A checking rule must be assigned in the checking control.
Question 30
Question
The __________ is the highest hierarchical level in the SAP S/4HANA application.
Please choose the correct answer
Answer
-
Storage location
-
Client
-
Plant
-
Company code
Question 31
Question
How many variants can be created for a variant BOM?
Please choose the correct answer.
Question 32
Question
What is the purpose of a reporting point confirmation in repetitive manufacturing?
There are 2 correct answers to this question.
Answer
-
To provide timely updates of inventory management for the staged components
-
To determine the work in progress along the production line
-
To stage different components for a production line simultaneously
-
To reduce the total production lead time for along production line
Question 33
Question
What are typical characteristics of make-to-stock production?
There are 2 correct answers to this question.
Answer
-
Sales order specific procurement
-
Sales order specific stock
-
Unrestricted use stock
-
Planned independent requirements for a finished product trigger its production
Question 34
Question
Which methods can you use achieve a feasible production planning case of capacity constraints?
There are 3 correct answers to this question.
Answer
-
Execute a new production planning run.
-
Reduce the planning window.
-
Select an alternative mode on a resource.
-
Form optimal sequences to reduce setup times.
-
Adjust the available capacity.
Question 35
Question
Which of the following statements describe the Monitor Work Center Schedules app?
There are 2 correct answers too this question.
Answer
-
It is a tool for dispatching, rescheduling, or deallocating several bottleneck operations on pacemaker work centers simultaneously in a graphical chart.
-
It is a tool for dispatching, rescheduling, or deallocating operations not only on pacemaker works centers but on all work centers in a defined area of responsibility.
-
It is a tool for dispatching, rescheduling, or deallocating individual bottleneck operations on pacemaker work centers in a graphical chart.
-
It is a tool to analyze the schedule of operations in a graphical chart.
Question 36
Question
What is a typical transportation processing SAP Transportation Management?
Please choose the correct answer.
Answer
-
Transportation Planning, Transportation Execution, Order Management, Freight Costing and Settlement, Analytics and Reporting
-
Transportation Planning, Order Management, Transportation Execution, Freight Costing and Settlement, Analytics and Reporting
-
Order Management, Transportation Planning, Freight Costing and Settlement, Transportation Execution, Analytics and Reporting
-
Order Management, Transportation Planning, Transportation Execution, Freight Costing and Settlement, Analytics and Reporting
Question 37
Question
In comparison between classic MRP and MRP Live, which planning mode is removed in MRP Live?
Please choose the correct answer.
Answer
-
Delete and Recreate Planning Data
-
Adapt Planning Data (Normal Mode)
-
Reexplode BOM and Routing
Question 38
Question
Where do you maintain the duration of a production operation?
Please choose the correct answer.
Answer
-
Routing
-
Bill of material (BOM)
-
Work instructions
-
Material master
Question 39
Question
What are the main processes of the embedded PP/OS in SAP S/4HANA?
There are 2 correct answers to this question.
Answer
-
Source determination for external procurement
-
Calculation of inventory buffer size
-
Long-term production planning
-
Optimization of the production plan
Question 40
Question
For what production type are production orders used?
Please choose the correct answer.
Answer
-
Period and quantity-oriented production
-
Discrete manufacturing processes
-
Replenishment controlled by control cycles
-
Process manufacturing processes
Question 41
Question
Which of the following production types is based on control cycles?
Please choose the correct answer.
Question 42
Question
An issue storage location was NOT found through the work center, bill of material (BOM) item, or material master. What determines whether the storage location can be derived from the production version?
Please choose the correct answer.
Answer
-
Plant Data
-
MRP Group
-
MRP Profile
-
MRP Controller
Question 43
Question
What does the Material Requirements Planning run trigger?
There are 2 correct answers to this question.
Answer
-
The creation of planned requirements
-
The creation of planned independent requirements
-
The creation of planned orders
-
The creation of production orders
Question 44
Question
Which of the following statements are true for make-to-order production?
There are 2 correct answers to this question.
Answer
-
Planning assemblies can be combined with the Make-to-Order concept.
-
Sales orders are fulfilled by anonymous warehouse stock.
-
Planned independent requirements always trigger final assembly.
-
Sales orders always trigger production.
Question 45
Question
With reference to MTO planning strategies, which of the following statements are correct?
Please choose the correct answer.
Answer
-
Both A and B are correct.
-
Only answer A is correct.
-
MTO strategies should always be combined with lot-size key EX (lot-for-lot).
-
Rounding values should not be used.
Question 46
Question
In the Schedule Production app, which settings can you make in the planning strategy?
There are 3 correct answers to this question.
Answer
-
Planning mode (bucket/sequence)
-
Direction (forward/backward)
-
Scheduling control (finite/infinite)
-
Finiteness level (0...1)
-
Fixed pegging (on/off)
Question 47
Question
Which of the following is an advantage of MRP Live and NOT available in classical MRP?
Please choose the correct answer.
Answer
-
MRP Live can plan materials with recursive BOMs
-
MRP Live can priorities demand from sales orders
-
MRP Live can propose alternative solutions
-
MRP Live can create production orders automatically
Question 48
Question
Which of following can be created or changed by the PP-DS planning runs automatically or manually?
There are 2 correct answers to this question.
Question 49
Question
Which of the following functions can be performed when the production order has the status “Created” (CRTD)?
Please choose the correct answer.
Answer
-
A user trigger material availability check via mass processing (transaction COHV)
-
A user trigger printing of shop floor paper manually (transaction CO02).
-
A user can trigger material staging via mass processing (transaction COHV).
-
A user can schedule a background job to release production orders (transaction COOIS).
Question 50
Question
Where can you find the latest in version of the Simplification List for SAP S/4HANA?
Please choose the correct answer.
Question 51
Question
Which time elements are part of a routing operation?
There are 3 correct answers to this question.
Answer
-
Queue time
-
Float before production
-
Wait time
-
Pick/pack time
-
Move time
Question 52
Question
What do you need to consider when working with material master numbering in SAP S/4HANA?
There are 2 correct answers to this question.
Answer
-
Material numbering is defined cross-client.
-
The maximum material number length is 18 for external numbers and 18 for internal numbers.
-
The maximum material length is 40 for external numbers and 18 for internal numbers.
-
Material numbering is defined at client level.
Question 53
Question
In which of the following can you find the main items and tasks of PP/DS planning?
There are 2 correct answers to this question.
Answer
-
Demand forecasting
-
Cross-location, period-based planning
-
Location-related capacity planning
-
Location-related material requirements planning
Question 54
Question
A customer is considering switching from order-related settlement to product-related settlement. What are capabilities of cost collectors?
There are 2 correct answers to this question.
Answer
-
They can be used for manufacturing with collective orders.
-
They can be created automatically during month end process.
-
They can be used for repetitive manufacturing.
-
They can be applied to make-to-stock production order.
Question 55
Question
What are the options for transferring data to SAP S/4HANA with the SAP S/4HANA Migration Cockpit?
There are 2 correct answers to this question.
Answer
-
XML files
-
Temporary tables
-
Staging tables
-
CSV files
Question 56
Question
In the Manage Shortage view of the new SAP Fiori app “Monitor Material Coverage”, what do the stars indicate?
Please choose the correct answer.
Answer
-
The presence of firmed planned orders
-
The presence of production orders
-
The viability of the proposed solution
-
The priority of the proposed solution
Question 57
Question
What are the three layers in the SAP Best Practices Content for SAP S/4HANA?
There are 3 correct answers to this question.
Answer
-
Building Blocks
-
Process Flows
-
Test Scripts
-
Solution Package
-
Scope Items
Question 58
Question
Which statement is correct? If you want to perform capacity planning for planned orders, then execute the MRP Live run with:
Please choose the correct answer.
Answer
-
Basic date scheduling
-
Lead-time scheduling
-
Finite scheduling
-
Midpoint scheduling
Question 59
Question
Which statements are correct with reference to BOMs?
There are 2 correct answers to this question.
Answer
-
The BOM status shows which application areas the BOM can be used in.
-
Net ID should be checked if the component is the same as the higher-level assembly.
-
The system will assign a low-level code for each material in the BOM structure.
-
Phantom assemblies will have the technical type P.
Question 60
Question
When do you recommend the use of repetitive manufacturing?
There are 2 correct answers to this question.
Answer
-
High product complexity
-
Low product complexity
-
High product stability
-
Low product stability
Question 61
Question
What is the purpose of collective orders?
Please choose the correct answer.
Answer
-
To post production costs on a cost collector instead of the production order
-
To manage production orders for an entire finished production multiple levels
-
To combine order management of co-products and by-products with the main product
-
To post any component withdrawals single back flush with order confirmation
Question 62
Question
When you define the process instruction category, you have to assign a process instruction type to enable the system to process the data accordingly.What are the different process instruction types available?
There are 3 correct answers to this question.
Answer
-
Process groups
-
Dynamic function calls
-
Universal
-
Calculations
Question 63
Question
Before a user can add multiple production versions in a material master, what information should be collected?
There are 3 correct answers to this question.
Answer
-
BOM status
-
Validity dates
-
Work center hierarchy
-
Task list group number
-
Lot sizes
Question 64
Question
What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning?
There are 2 correct answers to this question.
Answer
-
The work center has several individual capacities.
-
Alternative resources are fully occupied.
-
The Change Planning Direct on indicator is set.
-
The planning strategy is infinite.
Question 65
Question
Which SAP solutions can be used for forecasting in Supply Chain Planning?
There are 2 correct answers to this question.
Answer
-
Integrated Business Planning (IBP)
-
Capacity Requirements Planning (CRP)
-
Material Requirements Planning (MRP)
-
Supply Chain Management (SCM)
Question 66
Question
Which of the following are master data objects for kanban?
There are 2 correct answers to this question.
Question 67
Question
Which unit of measure is the stock keeping unit?
Please choose the correct answer.
Answer
-
Unit of issue
-
Order unit
-
Sales unit
-
Base unit of measure
Question 68
Question
Which data model changes have been implemented in Sales and Distribution?
There are 3 correct answers to this question.
Answer
-
Elimination of customer master tables
-
Elimination of output condition tables
-
Elimination of document index tables
-
Elimination of status tables
-
Elimination of LIS tables for rebates
Question 69
Question
What does forecasting in the demand planning cycle include?
There are 3 correct answers to this question.
Answer
-
One-off events
-
Past quotation quantities
-
Past procurement quantities
-
Past sales order quantities
-
Market intelligence
Question 70
Question
What are the requirements for working with a co-product?
There are 2 correct answers to this question.
Answer
-
The indicator in the material MRP data
-
The indicator in the material BOM header
-
The indicator in the routing header
-
The indicator in the material BOM item
Question 71
Question
A configurable material is a material for which different variants are possible. Identify all the planning strategies for configurable materials.
Please select all the correct answers that apply.
Answer
-
Planning variants with a planning material (Strategy 65)
-
MTO production for material variants (Strategy 26)
-
MTO production with configuration (Strategy 25)
-
Planning variants without final assembly (Strategy 55)
Question 72
Question
Your customer wants to include restricted-use stock as a potential receipt in the existing ATP check for component availability.
Which information is required to implement this change request in the scope of check?
There are 2 correct answers to this question.
Answer
-
The checking rule from the business application
-
The ATP category for restricted-use stock
-
The checking group from the material master
-
The checking control for the order type
Question 73
Question
What is the sequence of the five steps of Demand-Driven Replenishment in SAP S/4HANA?
Please choose the correct answer.
Answer
-
Analytics, buffer positioning, buffer sizing, replenishment planning, replenishment execution
-
Analytics, replenishment planning, replenishment execution, buffer positioning, buffer sizing
-
Analytics, buffer positioning, replenishment planning, replenishment execution, buffer sizing
-
Analytics, buffer positioning, replenishment planning, buffer sizing, replenishment execution
Question 74
Question
When do you maintain the work center that represents the production line for repetitive manufacturing?
There are 2 correct answers to this question.
Question 75
Question
You want to create a production order from a planned order. What methods could you use?
There are 2 correct answers to this question.
Answer
-
Order release
-
Individual conversion
-
Partial conversion
-
Full conversion
Question 76
Question
What does it mean for the production planner when MRP works with infinite capacities?
Please choose the correct answer.
Answer
-
MRP creates capacity requirements only if the work center has sufficient capacity.
-
MRP creates capacity requirements without checking the capacity of a work center.
-
MRP assigns capacity requirements automatically to work center is with the earliest available capacity.
-
MRP assigns capacity requirements automatically after the last scheduled order on a work center.
Question 77
Question
The production is based on the forecast for finished product, and the stock is expected to be available in inventory before the customer order. You want to quickly react to the customer requirement by increasing the production.
Which planning strategy should be selected?
Please choose the correct answer.
Answer
-
Planning strategy 70: Planning at assembly level
-
Planning strategy 50: Planning without final assembly
-
Planning strategy 40: Planning with final assembly
-
Planning strategy 20: Make-to-order production
Question 78
Question
Which are the possible restrictions of MRP Live?
There are 2 correct answers too this question.
Answer
-
Using the Advanced planning flag enables select materials in embedded PPDS to be treated separately in MRP Live on SAP HANA.
-
Time-phased planning isn't yet supported in MRP Live on SAP HANA.
-
Production version only considers the first BOM alternatives for planning in MRP Live on SAP HANA.
-
Configurable materials aren't supported in MRP Live on SAP HANA.